Chronology

2013 JULY Final Completion of the Ashta Project and start of the operation phase as defined in the Concession Agreement
- APRIL Start of electricity supply to KESH in line with the Offtake Agreement
- MARCH Substantial completion of the Ashta Project as defined in the Concession Agreement
2012 SEPTEMBER Test operation Ashta 1 completed and inaguration ceremony
- JUNE First electricity fed into the grid
- MAY Test operation started
- APRIL Flooding of the pit
2011 AUGUST First Hydromatrix®- Turbines installed
2010 AUGUST Shareholders’ agreement signed
- JANUARY Construction permit and start of construction works
2009 APRIL EIA concluded positively
2008 DECEMBER Energji Ashta Shpk founded
- SEPTEMBER Concession Contract signed