Chronology
Albanian government opens new tender on the project
Verbund and its innovative concept wins the tender
Concession agreement for the Ashta project is signed between Verbund and METE – Ministry of Economy, Trade and Energy
Start of first analyses for project pre-construction phase and permits
Establishment of project company Energji Ashta, a 100% subsidiary of Verbund
Urban Study is granted
Ministry of Environment grants Enivronmental Permit
Albanian System Operator OST grants Grid Connection Permit
National Albanian Board of International Commitee for Large Dams accepts project design
Documents for Energy Licence are submitted
Signing of agreement for electromechanical equipment between “Energji Ashta” and “Andritz Hydro”
Documents for Construction Permit are submitted
Site Permit is granted
Energy License is granted
Construction Permit is granted
Start of Construction